Re: [cross-project-issues-dev] Be sure to stay on the Helios train ...

>  I'll keep you updated.

That's the key to Release Train ... I appreciate everyone keeping us all 
informed. 

In case its not obvious (and, I'm sure it is not) the first three 
milestones have a two week "window" for projects to get into the build ... 
so we have until end of next week. 

So, next week is when I'll start to (try) and remove projects that aren't 
building ... just to allow those that can build to build to completion. At 
that time, there may be complications with dependancies -- if someone 
depends on you they'll have to be removed also -- but, we'll do what we 
can, and add projects back in when they are ready. 

Thanks again for the updates. 