Here it is again (take 3), with fix for a missing week in M7. Allocated one more week in M7 to compensate for EclipseCon distraction.

M1 - August 8, 2008 (6 weeks)
>>>  (3.4.1/Ganymede-SR1 +0 dates:  RC1-September 1, RC2-September 8, RC3-September 15)
M2 - September 19, 2008 (6 weeks) - PLANNING
M3 - October 31, 2008 (6 weeks) - DEV
M4 - December 12, 2008 (6 weeks) - DEV
M5 - January 30, 2009 (7 weeks) - MAJOR FEATURE WORK COMPLETED
>>>  (3.4.2/Ganymede-SR2 +0 dates:  RC1-February 2, RC2-February 9, RC3-February 16)
M6 - March 13, 2009 (6 weeks) - API FREEZE, FEATURE TUNING, I18N & ACCESSIBILITY
>>>  (EclipseCon March 23-27)
M7 - May 1st, 2009 (7 weeks) - PERFORMANCE & POLISH, BEST EFFORT ON DOC
RC1 (2 weeks) - May 15, 2009
RC2 (1 week) - May 22, 2009
RC3 (1 week) - May 29, 2009
RC4 (1 week) - June 5, 2009





__________________


Already found a typo in M1:


M1 - August 8, 2008
M2 - September 19, 2008
M3 - October 31, 2008
M4 - December 12, 2008
M5 - January 30, 2009 (one extra week to compensate for Christmas break)
M6 - March 13, 2009
(EclipseCon March 23-27)
M7 - April 24, 2009
RC1 - May 15, 2009
RC2 - May 22, 2009
RC3 - May 29, 2009
RC4 - June 5, 2009
Final - June 12, 2009




 

__________________

In parallel of the discussion for a good name for the next iteration, I would like to know what its staging might look like (at least for the +0 dates) ?
Here are my first suggestions in case none was made already:

M1 - August 10, 2008
M2 - September 19, 2008
M3 - October 31, 2008
M4 - December 12, 2008
M5 - January 30, 2009 (one extra week to compensate for Christmas break)
M6 - March 13, 2009
(EclipseCon March 23-27)
M7 - April 24, 2009
RC1 - May 15, 2009
RC2 - May 22, 2009
RC3 - May 29, 2009
RC4 - June 5, 2009
Final - June 12, 2009



Sauf indication contraire ci-dessus:/ Unless stated otherwise above:
Compagnie IBM France
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie
RCS Nanterre 552 118 465
Forme Sociale : S.A.S.
Capital Social : 542.737.118 euros
SIREN/SIRET : 552 118 465 02430



Sauf indication contraire ci-dessus:/ Unless stated otherwise above:
Compagnie IBM France
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie
RCS Nanterre 552 118 465
Forme Sociale : S.A.S.
Capital Social : 542.737.118 euros
SIREN/SIRET : 552 118 465 02430


_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev



Sauf indication contraire ci-dessus:/ Unless stated otherwise above:
Compagnie IBM France
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 Courbevoie
RCS Nanterre 552 118 465
Forme Sociale : S.A.S.
Capital Social : 542.737.118 euros
SIREN/SIRET : 552 118 465 02430


Back to the top