Re: [cross-project-issues-dev] GEF RC6 - wasn't in the Callisto schedule...

DTP: RC5 as it is currently in Callisto will be 0.9. (I will update only
the site.xml file to change the category text.)

Regards,
John Graham
Eclipse Data Tools Platform PMC Chair
Staff Software Engineer, Sybase, Inc.
http://dataplat.blogspot.com/



                                                                           
             David M Williams                                              
             <david_williams@u                                             
             s.ibm.com>                                                 To 
             Sent by:                  Cross project issues                
             cross-project-iss         <cross-project-issues-dev@eclipse.o 
             ues-dev-bounces@e         rg>                                 
             clipse.org                                                 cc 
                                                                           
                                                                   Subject 
             06/27/2006 01:19          Re: [cross-project-issues-dev] GEF  
             PM                        RC6 - wasn't in the     Callisto    
                                       schedule...                         
                                                                           
             Please respond to                                             
               Cross project                                               
                  issues                                                   
             <cross-project-is                                             
             sues-dev@eclipse.                                             
                   org>                                                    
                                                                           
                                                                           





Thanks Steve, I updated the plan, just to be exact.

How's everyone else doing? One day to go ... no need to wait to last
minute! ::)

These first two project have confirmed updates are coming (today).

WTP (RC6)
GEF (RC6)

These 5 list in the plan that updates are coming ... still accurate?

CDT (RC4)
EMF (RC9a)
BIRT (RC6)
GMF (RC6)
TPTP (RC6)





                                                                           
 Steven Shaw                                                               
 <steveshaw@xxxxxxxxxx>                                                    
 Sent by:                                                               To 
 cross-project-issues-dev-bounce              cross-project-issues-dev@ecl 
 s@xxxxxxxxxxx                                ipse.org                     
                                                                        cc 
                                                                           
 06/27/2006 01:40 PM                                               Subject 
                                              [cross-project-issues-dev]   
                                              GEF RC6 - wasn't in the      
        Please respond to                     Callisto        schedule...  
       Cross project issues                                                
  <cross-project-issues-dev@ecli                                           
             pse.org>                                                      
                                                                           
                                                                           
                                                                           
                                                                           






Hello,

I noticed that Callisto wasn't listing an RC6 candidate for GEF in the
"Callisto Plan Summary".
http://wiki.eclipse.org/index.php/Callisto_Plan_Summary

Hopefully this isn't a problem, but we are going to produce an RC6 build
for GEF.  There aren't any production bits changes in this, only some
feature copyright and about box information updates.  Dependent projects
don't need to rebuild based on this spin.

bugzilla addressed:
https://bugs.eclipse.org/bugs/show_bug.cgi?id=147440

This will be posted shortly and then promoted to 3.2 GA status tommorrow.

Regards,

Steve.
________________________________________
Steven R. Shaw
Rational Modeling Platform Diagram Layer Lead
Rational Software | IBM Software Group
770 Palladium Drive, Kanata, ON, Canada, K2V 1C8
tel: 613.591.7979
steveshaw@xxxxxx.com_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev




Back to the top