Title: COSMOS i11 testing - QA Execution Plan

All,

Pl. find QA execution plan for iteration 11(i11) testing (16th Jun - 27th Jun'08):

Primary Tasks:
============

        - org.eclipse.cosmos.me.dmtoolkit.tests/ManagementEnablement.UI.dmtoolkit.testsuite
        - SML Tooling - adhoc UI testing for editor/validator/import/export features

Secondary Tasks:
==============

  • Basic operational efficiency tests (limited performance tests)

Test cases for all above activities can be found at - http://wiki.eclipse.org/COSMOS_QA_End2End_Tests and the results/status for all these activities

will be captured at - http://wiki.eclipse.org/COSMOS_i11_QA_Phase_Execution

Pl. note if there is any delay in providing i11 candidate driver for QA testing (or) if there is any additional build during QA execution time, then some

part of secondary tasks (performance testing) will be deferred to post june 27.