Re: [cdt-dev] Remaining fixes for 8.1.2

PS keep in mind that eclipse.org servers are moving on Saturday Feb 9, leaving the repos unreachable,

so there’s a risk that week-end work can’t make it into the Monday builds and 8.1.2 should best

be done Friday night.

 

Thanks,

Martin

--

Martin Oberhuber, SMTS / Product Architect – Development Tools, Wind River

direct +43.662.457915.85  fax +43.662.457915.6

 

From: cdt-dev-bounces@xxxxxxxxxxx [mailto:cdt-dev-bounces@xxxxxxxxxxx] On Behalf Of Oberhuber, Martin
Sent: Thursday, February 07, 2013 8:35 AM
To: cdt-dev@xxxxxxxxxxx
Subject: [cdt-dev] Remaining fixes for 8.1.2

 

Hi all,

 

Only few days are left for the last 8.1.2 build, currently there’s 2 open bugs assigned an 8.1.2 target:

http://bit.ly/X7eRrh

 

If anybody knows about other must-fix issues, it would be good setting the target milestone so

we have a complete query. Getting a top robust and stable 8.1.2 is important for us at WindRiver

(and others too, I’d hope J) so some extra testing would also be good.

 

Thanks,

Martin

--

Martin Oberhuber, SMTS / Product Architect – Development Tools, Wind River

direct +43.662.457915.85  fax +43.662.457915.6

 