[cdt-dev] FW: Updated Ganymede Milestone & RC Dates ::For Review
|
Hey gang,
Here's a proposed schedule for the remaining milestones
and release candidates for Ganymede. CDT 5.0 fits in the +1 column of the
table.
Please let me know if you have any objections and I'll
raise them to the palnning council.
Thanks,
Doug Schaefer
Engineering Manager, Wind River
Systems
and Eclipse CDT Project
Lead
Everyone:
I've taken the liberty of filling in the missing
dates in the Ganymede M & RC table [1], and maked these as 'tentative / not
yet approved'.
[1]
http://wiki.eclipse.org/Ganymede#Milestones_and_Release_CandidatesWe
could have a F2F vote on these at EclipseCON, but it might be just as effective
to do a mailing list vote -- the usual approach of "if no one complains and a
few weeks go by, the resolution passes by default."
At any rate, the
dates are there. Have a look and complain or adjust them if necessary. ;-)
Nick