[cdt-dev] FW: Updated Ganymede Milestone & RC Dates ::For Review

Hey gang,
 
Here's a proposed schedule for the remaining milestones and release candidates for Ganymede. CDT 5.0 fits in the +1 column of the table.
 
Please let me know if you have any objections and I'll raise them to the palnning council.
 
Thanks,
Doug Schaefer
Engineering Manager, Wind River Systems
and Eclipse CDT Project Lead
 


From: cross-project-issues-dev-bounces@xxxxxxxxxxx [mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of Nick Boldt
Sent: Wednesday, January 09, 2008 3:56 PM
To: eclipse. org-planning-council; Cross project issues
Subject: [cross-project-issues-dev] Updated Ganymede Milestone & RC Dates ::For Review

Everyone:

I've taken the liberty of filling in the missing dates in the Ganymede M & RC table [1], and maked these as 'tentative / not yet approved'.

[1] http://wiki.eclipse.org/Ganymede#Milestones_and_Release_Candidates

We could have a F2F vote on these at EclipseCON, but it might be just as effective to do a mailing list vote -- the usual approach of "if no one complains and a few weeks go by, the resolution passes by default."

At any rate, the dates are there. Have a look and complain or adjust them if necessary. ;-)

Nick
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev

Back to the top