To be able to plan enhancements and assign bugs in Bugzilla, new target milestones are created in Bugzilla for the following 2.1 release plan. Please use them accordingly. The first and only milestone for BIRT
2.1 is M5. We had 2.1.0M1 to 2.1.0M3
milestones in Bugzilla, they are out dated now. Please stop using them. I will move all M1 bugs to M5.
Release milestones
The
Eclipse BIRT 2.1 release milestones will be synchronized with the Eclipse Callisto simultaneous release. The first BIRT 2.1 milestone
will be designated M5 in order to synchronize with the Callisto
simultaneus release numbering. All release
deliverables will be available for download as soon as the release has been
tested and validated in the target operating configurations listed below.
Release
milestones:
- Friday, March 3, 2006 BIRT 2.1 M5
- Friday, April 7, 2006 BIRT 2.1 Release
Candidate 0
- Friday, April 14, 2006 BIRT 2.1 Release
Candidate 1
- Friday, April 28, 2006 BIRT 2.1 Release
Candidate 2
- Friday, May 12, 2006 BIRT 2.1 Release
Candidate 3
- Friday, May 26, 2006 BIRT 2.1 Release
Candidate 4
- Friday, June 16, 2006 BIRT 2.1 Release
Candidate 5
- Wednesday, June 28, 2006 BIRT 2.1
Release Candidate 6
Our target is to complete and release BIRT 2.1 with the Callisto simultaneous release, currently targeted for late
June 2006.
Thanks
Wenfeng Li
Eclipse BIRT PMC
Actuate Corporation -
Engineering
|