[alf-events] Eclipse ALF Planning Meeting Minutes 2/24

 Attendees:  Kelly Shaw, Bob Brady, Tim Buss, Brian Carroll, Eric
Minick, Cliff Utstein, Scott McGrath, John Scalisi, Christopher Rollo


Team agreed on the following improvements to the demo/application for
EclipseCon (starts
3/20)

1 - Replace Service Flow - swap CVS for DM - Gives us open source
capability.  Team agrees this is a good addition for the EclipseCon
demo.
Tasks:
 - CVS Service Flow - Tim
 - Interface/Service to have Event Manager auto reload the Event Map -
Tim
 - Call Interface/Service - Tim
 - Install & Configure CVS - Rollo

* Team would like to eventually have a complete open source solution
path, but given the time frame remaining to Eclipse Con we don't have
the time to do all this, but we can add in CVS & Bugzilla in that
timeframe.  Requirements team will continue to discuss the full use case
for 1.0 release.

*** Cliff @ AccuRev will investigate if they can also create a Service
to replace DM using the same WSDL to show this functionality also.  Will
discuss with the details with Tim.  

2 - Expected Build Failure & submit bug to Bugzilla - Also shows open
source capability.  Team agrees this is a good addition for the
EclipseCon demo.
Tasks:
 - Add options to TT Flow to select broken build - Tim
 - Extend DM or CVS "Get" to get the Broken Project - Tim
 - Catalyst Pass failed build status - Steve
 - Modify TT Service Flow to raise Event to run the Update Bugzilla SF -
Tim
 - New Service Flow for Bugzilla (command line Service?) - Tim or Steve
 - Install & configure Bugzilla - Rollo
 - Adjust current Event tool extension data to normalize - Tim
 - Add failure from the test tools - Bob

3 - Branching for Test Options - Team agrees this is a good addition for
the EclipseCon demo.
Tasks:
 - Add options to TT to specify what you want to do for test - Tim
 - Pass data from TT - Tim
 - Branching of the BPEL flows - Tim implement, ***Bob recommend what
can be branched
 - Possibly options for scan to branch? - at least add the option to
scan or not to scan - ***John S provide failure status or results of
this?  Tim discuss with John.  

4 - Unexpected Build Failure - Emphasize why this is different than
scripting. Add this if time allows.
  - Build a sample BPEL map that shows compensation

5 - Continue work on Service Stubs and documentation on how to configure
system - target finishing this by EclipseCon or shortly thereafter so
folks can download and see ALF hands-on
 - Vendor finalize stubs
 - Commit to CVS
 - Finalizing packaging

6 - Compuware Corona use case - Continue working with this team to
either add a demo or a "story" about the synergy of the projects.


***EclipseCon Contributors w/Products - Please also check your licenses
to ensure they won't expire before/during Eclipse Con.  

Mirinda will incorporate these tasks into our project plan and post that
early next week.  Target is to complete all tasks by 3/10 and spend the
final week working out any last minute kinks.  We'll spend the next 3
meetings finalizing work for EclipseCon and then start planning the
tasks/plans for the next deliverable.

**********************************************************************
This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all copies of the original message.