[alf-events] RE: Eclipse ALF POC Schedule Meeting minutes Fri 1/6
|
Title: Eclipse ALF POC Schedule Meeting Tue 10/18 8:00 am PT
Attendees: Serena, Segue,
Catalyst
Integration Status - target
completion next Friday
- Able to launch BPEL flows from TT through event
manager
- Able to call TeamTrack, Segue, and Catalyst
Services
- Tim received Delivery of Dimensions Service &
will review this
- Not sure
the status of the Secure Services - John's back on 1/11 and we'll check in with
him then
Need:
- Catalyst to call the Event Batch to say the
build is done to trigger the next part of the process. Tim/Steve will discuss how to do this to get Steve going. Bob will take advantage of this
as well to tell him when the test is completed - Tim will send Bob the details
on this as well.
Next Steps:
- Come up with a working stub set that illustrates
the POC to upload to Eclipse so we don't need to upload all the products, etc. Need to figure out who owns what to do this.
- Event Manager code will be uploaded prior to
Validation. Also get the working stubs uploaded. Tim to
coordinate this.
- Create a recorded presentation of the POC to upload
to Eclipse as well.
- Present the POC to the Bjorn/Mike from the Eclipse
board early Feb. (Kevin coordinating this date). Then do a
presentation to the larger Board about the POC and next steps,
etc.
- Planning to do a presentation at Eclipse Con in
March - likely include additional functionality that we'll
implement.
Other Status:
- Design for ALF single sign on in progress, document
~50 pages already. Planning to send this to team next week.
Separating the implementation decisions from the architecture. Working to
define the architecture so the team can choose the right
implementation.
- Code review of Event Manager in
progress. Focus is on changes to multi-threading/tasking at
present.
- Documenting the process for use of Bugzilla
and Code Management.
- ALF Vocabularies (Dimensions, etc.) in
progress.
- Serena working to create a testing strategy for
future ALF implementations.
- Bob moving code to the machine, so starting &
stopping the Services at present. Will let Tim know when he's done
today.
Steve is out Monday/Tuesday (will be at Serena
Tuesday).
Check out the recent proposal by Compuware. It
discusses interaction with ALF. We should evaluate how we can take
advantage of this as well.
Meeting next week will be run by Tim.
From: Mirinda Lowe
Sent: Thursday,
January 05, 2006 4:52 PM
To: Mirinda Lowe; 'ALF Developer Mailing List'; 'ALF project announcements'; 'ALF project requirements
discussions'
Subject: Eclipse ALF POC Schedule Meeting agenda Fri 1/6
11:00am PT
All,
There will be a schedule
meeting tomorrow at 11:00 a.m. PT for the ALF Proof of
Concept. Please plan to attend this if you are contributing to the POC or
are interested in hearing this information.
Call in number: 1-303-928-3232; ID
6723351
Agenda:
Discuss current status & issues on
integration
Thanks
Mirinda
Lowe
**********************************************************************
This email and any files transmitted with it are confidential and
intended solely for the use of the individual or entity to whom they
are addressed. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all copies of the original message.