[alf-events] Eclipse ALF POC Schedule Minutes Fri 10/28

Title: Eclipse ALF POC Schedule Meeting Tue 10/18 8:00 am PT
Attendees:  Serena, Segue, Secure, Catalyst
 
Reviewed schedule & added dates/tasks.  See updated schedule online. 
 
Key Decisions/Actions: (actions in bold)
 
Software installation will be divided into 2 tasks - 1 to coincide with the WSDL or Stub completion and 1 to coincide with the Service completion.  Status - completed in current project plan.
 
Sample project will be Eclipse project in Java.  Must be testable, buildable, scanable, runable.  Homework for all - come up with suggestions that we can decide at next meeting, possibly some that are currently being used by the POC participants now.  Try to keep it a small project so it runs fairly quickly.
 
POC should strive to run through a few scenarios through the same service flow - build passes, build fails, etc. This may not be possible by the POC, but we might want to add a 2nd milestone end-January to do some of the compensating services or possibly in March for the Eclipse conference.  There are also other partners that want to participate in demos that would be good to get in some additional demos. We'll need to look at adding tasks and a date for this in the near future.  Mirinda will work with the team to plan this once the POC is planned.
 
All POC participants will need a VMWare image.  Working to figure out how we get this license to all.  May need to build 4 different images (and install software 4 times, etc.)  One way is if everyone has the Select license from Microsoft.  Tim will follow up via email with the POC participants.  If anyone has ideas, let Tim know.
 
Need to verify what version of Java we will run.  Also TomCat.  Tim will send out a proposed list of versions for the team to review
 
All POC participants review the updated schedule online.  Red items are due this week.  Blue items we still need to finalize dates for.  Purple items may be removed.


From: alf-events-bounces@xxxxxxxxxxx [mailto:alf-events-bounces@xxxxxxxxxxx] On Behalf Of Mirinda Lowe
Sent: Thursday, October 27, 2005 5:32 PM
To: ALF project announcements; alf-dev@xxxxxxxxxxx; alf-req@xxxxxxxxxxx
Subject: RE: [alf-events] Eclipse ALF POC Schedule Meeting Fri 10/28 11:00 am PT

All,

There will be a schedule meeting tomorrow Friday 10/28 at 11:00 a.m. PT for the ALF Proof of Concept.  Please plan to attend this if you are contributing to the POC or are interested in hearing this information.

Call in number: 1-303-928-3232; ID 6723351

Agenda:

Review key POC tasks, agree to tasks & ownership, and commit to dates for each task

 - Hardware/software preparation

 - ALF Logging

 - Web Services

Any open issues or tasks to resolve to keep moving on tasks? 

Thanks
Mirinda Lowe

**********************************************************************

This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all copies of the original message.