Attendees:  Bob Brady @ Segue, John Streiff @ Secure, Tim Buss & Mirinda
Lowe @Serena , Cliff Utstein & Matt Laudato @ Accurev


Team is finalizing preparations for next Thursday's Demo:

Tim removing the BPEL workaround - 1 remaining issue dealing with the
event batch that should be removed today.

Worked with Bob to make the Segue Service more flexible, allowing the
specification of which tests to run.  Now working as planned, with a bit
more flexibility.

Secure finalizing the view for the Scan Results.  Will have a page from
Secure to show their results - John's team working on this with Tim.

Issue with the tests not all succeeding once the scan was installed has
been resolved by Segue.


Next Steps After POC:

Start preparing the demo for Eclipse Con in March.  Would like to make
it more flexible so you can make more choices from the available actions
via the TT page.  Also look to add some additional use cases to the demo
to make it more robust and also to interact with some opensource tools
(e.g. Bugzilla, etc.)  We'll discuss this more next week in Thursday's
meeting.  Should evaluate putting more error handling in as well.  

Team discussed a general design issue where a BPEL flow launches a
single event to 1 of the vendor tools and the vendor tool carries out
several autonomous tasks.  An example is the Segue tool launches several
different tasks.  How does this get reported back to the Event Manager?
Should we launch several tasks to say that each one has started and one
event to say all tasks completed?  Segue is sending back several events
to say each task is completed.  This will be valuable for the move
forward to allow more choice over which tasks to run and for ALF future
design.  Need to have further discussions around the Event Design.
Mirinda will pass this onto Brian to discuss with the Architecture team
moving forward. 

Current plan is to have the 1.0 release ready to be approved by Eclipse
in the Fall of 2006.  Event Manager may be finalized sooner than that.
Will begin discussing the tasks/plans for this in next Thursday's
planning meeting.  

Accurev is working to download and build the Event Manager using a BPEL
engine and configure a few events to get started.  Will provide any
feedback/questions to the team.  

For the Planning portion of next Thursday's meeting, teams should come
prepared to discuss ideas for the POC2 in March @ Eclipse Con - possible
additional use cases, Open Source tools to integrate with, etc.  Also
the V 1.0 release in the Fall.  We'll begin planning both during that
session.



  


**********************************************************************
This email and any files transmitted with it are confidential and
intended solely for the use of the individual or entity to whom they
are addressed. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all copies of the original message.



Back to the top